Grant Expansion Update
Grant Update
12/10/24
December Grant Update
General Comments:
PES is proud to announce that an additional 1,800 locations now have the opportunity to access high-speed fiber optic internet!
Phase One
- Status: Complete
Phase Two
- Status: Complete
Phase Three
- Mainline Fiber Construction: 90% complete.
- Progress:
- The process of connecting fiber from the mainline to individual homes is ongoing but behind the original schedule.
- Subdivision Progress:
- Areas/Cabinets 1–3: Completed, but 15–20 locations have significant delays due to contractor-related errors.
- Area/Cabinet 4: Quality checks completed; several issues were identified and are being resolved, delaying installations.
- Area/Cabinet 8: Missed the quality check deadline, pushing installations to mid-January.
- Remaining areas in the northwest brown section: Installation now expected to begin in February, with completion projected by the end of March 2025.
Phase Four
- Pole Replacements:
- 67% complete (554 poles replaced out of 822 scheduled).
- PES crews, along with two contracted companies, are actively working on pole replacements.
- Mainline Fiber Construction:
- Began November 18, 2024, in the brown section.
- Scheduled to begin December 9, 2024, in the red section (ahead of schedule).
- Fiber work is being performed by the same crews responsible for Phase 1 and Phase 2.
Northeast Area
- Mainline Fiber Construction: 60% complete.
- Expected Service Availability: High-speed internet and phone service expected before March 2025.
This update highlights our ongoing commitment to expanding reliable, high-speed internet access across the community. Thank you for your patience as we work toward completing these projects.