Phase 1

  • Make-Ready – Right of Way/Vegetation cleared
  • Construction – Mainline Fiber Constructed
  • Splicing √
  • Installs 

Phase 1 is complete!

Phase 2

  • Make-Ready – Right of Way/Vegetation cleared
  • Construction – Mainline Fiber Construction In progress/99% Complete
  • SplicingIn progress 
  • InstallsIn progress

Phase 2 Waiting List is Open!

Phase 3

  • Make-Ready – Right of Way/Vegetation cleared
  • Construction – Mainline Fiber Construction In progress/40% Complete
  • SplicingIn Progress
  • InstallsIn Progress

Phase 3 Waiting List is Open!

Phase 4

  • Make-Ready – Right of Way/Vegetation cleared
  • Construction – Mainline Fiber Construction Set to begin in November and conclude by mid-April 2025
  • Splicingwill start as construction progresses
  • Installswill start after splicing and testing, Installs set to be completed by June 2025